ROGER REPORT:
---------------------------

2 flooring worker time 7.00 to 3.30 Installing
          Remove the sanded grout on the floor

2 electric workers time ?

4 advanced workers time 8.30 to 3.00 pm installing
           Sand the floor  on the basement

GBR crew
       Installing
       Putt plywood on the stair & putt drywall on the on the wall on bathroom mug

-----------------------
GINO REPORT:
-----------------------

Bevelloni:

I did not have Juan and his helper install today because the drive way leading to the garage was to muddy for the boomlift. They will start on Thursday  2/11 again.

Started demo of drywall of basement stairs getting ready for cutting the concrete.

Installed plywood on top of the drywall on the stairs to protect them from any damages when they start cutting the concrete.

Danny and helper finished the electrical work needed for the cabinets.

Gonzalo and helper finished living room grout work and now working in the front of the main stair case.

Honing finished in the basement but they still need to seal the floor. (they will be working in the kitchen and living room on Thursday morning while the other crew will be in the basement sealing the floor.