GINO REPORT:
------------------------
Bevelloni:
Juan and helper:
They are done with the GRFC's on the garage side of the house (they
took 2 1/2 days) Now they are working on the front of the house left side. They
will need until Friday to finish and then they will start sanding down all
GFRC's next week on Monday.
Jesse and Rigo:
Installing kitchen wok and making custom boxes for transformer
locations.
Oscar and Roger:
Driving Juan and helper with the boom lift and also working inside
the house with Roger on the stairs (installing plywood to protect the stairs.)
--------------------------
ROGER REPORT
--------------------------
2 stone workers time 700 to 500 installing
2 pcs gfrc on the side
remove the gfrc on the front
2 flooring workers time 700 to 330 Installing
Remove grout
4 advance workers time 700 to 330 Installing
Honing the basement & the second
floor