ELEANA REPORT 29

Marble Polishing:

PROGRESS REPORT IN PDF

Attached is the updated plan for the marble polishing at Beveloni as of today 3/29/10.

Here's a brief summary:

 

 Cabinets:

Crew is working on the Main Kitchen as of today. They were sorting and beginning the install of the base cabinets. See attached pictures of what was completed today.

 Front Canopy:

Michael Ni confirmed he will finish drawings this Wed 3/31/10. Our site meeting with him and all subs is tentatively scheduled for Monday 4/5/10.

 Low Voltage:

Dwight/DSE was a not reachable the past Saturday. He ended up apologizing to G and rescheduled to this Sat. Our low-voltage bidders are standing by to bid as soon as we get info from Dwight on what's been done and what's still needed. 

ROGER REPORT:

pic of 26 & 29                     

GBR crew installing

      8 base cabinet & bring all door on the basement & clean & demo the wall