2 flooring workers time 700 to 330 Installing
1 pcs granite grout
kimic
GBR crew
Arturo
Eleana
Zuli
Rigo
Gino
Roger
Jesse & Oscar Installing
Lager for the cabinet 2 box install & the
rest is ready
load the GBR truck
move the granite on the the basement
2 electric workers
-----------------------
Report By Gino
-----------------------
Bevelloni:
Danny and Helper:
Working in the wok, main and pantry area re-wiring and deleting. Danny
will be back on Wednesday and start working again. He has to finish his another
job really fast first.
Basement Stairs:
I have two bids the first one is for $1985.00 and the second one
is for $3800.00 do you want me to get started already???
Jesse and Rigo:
Installing Pantry cabinets and also making a mock up for the chimney.
Mock up is already done and is on the roof. We have a meeting with Vladimir in
the morning at 10am for him to look at it and they are also making a second mock
up per vladimir.
Roger:
Working on patching up drywalls where Danny is installing new wire and
re-moving wire.
Oscar:
Unloading cabinets that we brought back from Bevelloni at the warehouse
and staging them for next weeks delivery to Eleana's and Mike's house. Also
looking for your trash compactor for 724 Forest Green Drive.
Gonzalo and Helper:
Working at the first floor gallery way with the grout work. Basement is
already done with the grout work and chemic.