1
- Interior
living room & family room
-
Stone
7 pcs nn1
7 pcs nn
6 pcs rr4a
8 pcs ee4
4 pcs f1
& scaffold arrange in
front of hallway
time 7.00 to 5.00
7 stone workers |
2
- Interior
Family Room -
Stone
12 pcs nn
7 pcs nn1
2 pcs f2
2 pcs rr4a
2 pcs 4c
time 7.00 to 5.00
7 stone workers |
3
HOLIDAY |
4 |
|
5 |
6
- Interior
Family Room -
Stone
2pcs 4e
3 pcs 4d
3 pcs 4a
8 pcs 5e
& grout
time 7.00 to 5.00
7 stone workers |
7
- Interior
Family Room -
Stone
8 pcs ee4
12 pcs 5c
2 pcs 4a
& sanded grout
time 7.00 to 5.00
7 stone workers |
8
- Interior
Family Room -
Stone
21 pcs ee4
6 pcs 2b
30 pcs rr4a
time 7.00 to 5.00
7 stone workers
2 electric workers |
9
- Interior
Family Room
Pour Concrete @ Second Floor -
Stone
63 pcs rr4a
5 pcs ee5
7 stone workers |
10
- Interior
Family Room -
Exterior
35 pcs rr4a
3 pcs ee5 &
sanded grout
time 7.00 to 12.00
7 stone workers |
11 |
|
12 |
13
- Interior
Family
room
Flooring workers just measure & snap the floor
-
Exterior
7 pcs ee5
36 pcs rr4a
4 persons in morning & 3 in noon for
Jesus crew
7 flooring worker & 2 electric
time 7.00 to 5.00 & 3 haft day for Jesus |
14
- Interior
GBR - family room
7 workers for flooring: measuring the floor & snap
2 electric workers -
Exterior
7 Stone Workers
7.00 to 5.00 install 17 pcs cx
3 pcs rr4a
remove ee5 on rear of the house |
15
- Interior
7 Flooring Workers
2 Electric Workers -
Exterior
7 stone workers
10 pcs cx
8 pcs 2f
5 pcs
& the replace area on the back 8 pcs cc5
10 pcs rr4a small the
basement |
16
- Interior
8 pcs mb- cd-xco8 marble
7 Marble workers
3 Electric Workers -
Exterior
7 stone Workers
Install
8 pcsy2
8 pcs y3
27 pcs cc5
25 pcs cc4
& unload container |
17
- Interior
7.00 am to 12.00 pm - 7 workers
4 pieces mb -cd-xc08 marble -
Exterior
7 Stone Installer from 7.00 am to 02.00 pm
install
10 pcs ee4
21 pcs ee5
6 pcs mm
2 pcs y2
4 pcs y3 |
18 |
|
19 |
20
- Interior
7 Marble Installer from 7.00 am to 5.00 pm
4 pieces mb-cd-xc08
1 electrician
GBR - Dining Room
-
Exterior
7 Stone Installer from 7.00 am to 5.00 pm
13 pcs y
29 pcs ee5
8 pcs ee4
4 pcs mm |
21
- Interior
* 7 marble workers 07.00 am to 05.00 pm install
29 pcs bd-cbob 1pcs
cp-xco5
* GBR - Dining Room
* 2 electrical workers
* unload marble container shipment from Chino
- Exterior
7 Stone installer from 7 to 5pm |
22
- Interior
*7 workers flooring installing
3 pcs ce-wbo2
12 pcs bd-cbob
3 pcs cp-xco5
*2 Electric Workers
*GBR Dining Room -
Exterior
7 workers
43 pcs rr4a
2 pcs cx
2 pcs y3
3 pcs ee
& tree on the front
face of the house |
23
- Interior
* 7 Flooring 7 to 5pm
install
2 pcs mb-cp-xc07
1 pcs
mb-cp-xoo9
5 pcs mb-eb01
3 pcs mb-bd-bc03
*3 Air Condition Workers
*2 Electric Workers
*GBR
-
Exterior
7 stone workers from 7.00 am to 05.00 pm
Installing:
7 pcs mm2
9 pcs e1
15 pcs e |
24
- Interior
*7 Flooring 7.00 to 12.00 install
15 pcs mb-cd-eb01
2 pcs mb-bd-bc03
*3 air conditions workers complete relocate air return
duct 7.00 to 1.00 *GBR assemble 9 crowns & put back
one beam in dining room
-
Exterior
7 workers 7.00 to 12.00
install
15 pcs d
7 pcs d1 |
25 |
|
26 |
27
- Interior
Flooring 7.00 to 5.00pm install
3 pcs mb-bd-bc04
7 pcs mb-bd-bbor
1 pcs mb-gt-vbo2
15 pcs mb-cd-ebo1
GBR install one beam & labeling second floor
-
Exterior
7 Stone Installer from 7.00 to 5.00 install
4 pcs mm
9 pcs mm3
15 pcs z
7 pcs z2 |
28
- Interior
GBR
Marble Installer
Electric -
Exterior
Stone Installer |
29
- Interior
GBR
Marble Installer -
Exterior
Stone Installer |
30
- Interior
GBR
Marble
Electric
Miguel
- Exterior
Stone Installer |
31
- Interior
GBR
Marble -
Exterior
Stone |
|